江阴润阳储能技术有限公司由江阴长江投资集团投资设立,是一个专业生产太阳能光热发电设备和储能设备的制造企业,也是进行太阳能塔式发电系统设计咨询、方案制定、工程总承包的公司。
  公司地处江阴临港经济开发区,目前已建成个塔式光热发电的示范项目,同时成功组建了以生产石墨储能为主的光热储能设备制造企业。
  公司生产的储能设备引进了澳大利亚Solastor公司的专利技术。该技术目前是国际领先、国内填补空白的固态内置式储能技术,公司得到外方授权,是国际上该技术设备的唯一供应商,在国内则是该技术唯一的许可证使用商。
  今后公司将致力于发展成为光热储能行业的领跑者。
  集热器是由集热孔将定日镜反射的光能集中吸收,并由储热介质石墨进行储能,通过换热管进行热交换,将水变成工作蒸汽。

----------------------------------------------------------------------------------------------------------------------------------------------





    CSP Today – First of its kind CSP plant underway in Cyprus  



The following excerpt is from an article posted in CSP Today by Heba Hashem and Sam Phipps on 18th April, 2014.

An innovative 50 MW CSP plant that is due to be built in Cyprus with EU support could pave the way for its graphite based storage system elsewhere in the world, engineers say.
The EOS project, which will be sited at Alasa, in the Limassol district of the Mediterranean island, was proposed by the Cypriot government under the EU NER300 scheme and was approved in late March this year.
Utilising Australian company Solastor’s Concentrated Solar Thermal (CST) storage system, EOS will feature three-metre high tanks atop relatively low (20 metre) towers that stand at the centre of a bank of heliostats.
The steel tanks contain high purity graphite blocks, with water pumped through embedded coils of stainless steel pipes. Heat exchangers create super heated “dry” steam, which is discharged to a turbine to produce electricity for the power grid.
The steam is converted back to water, pumped into a holding tank and then back into the tower tank in a sealed system. “Solastor and the engineering contractor have a memorandum of understanding and we are just waiting for the finalising of the EU grant,” said a source close to the project. “We expect it to be between €47m and €60m, and the total cost of the plant will be about €175m.”

Project features

The EOS 50 MW CSP project will supply about 5 per cent of Cyprus’s electricity generation, with power on demand, even after sunset.
Each heliostat will be approximately 10 sq metres, with 100 to 120 reflectors per tower. This modular design is well suited to the uneven terrain of Cyprus, enabling modules to be positioned at various levels, on separate terraces, rather than on one vast expanse of flat land.
The plant will comprise up to 600 modules, a power station with two steam turbine generators, a switch sub-station to transmit energy to the national grid, and a series of steam condensers.
The heliostats will be toroidal and made of metal, covered with a form of silver foil, rather than the more usual glass. The super-heated steam generated by the array can either produce electricity via the steam turbine – for the national grid or to power specific installations – or it can provide “thermal input”: the industrial steam for processing, heating/cooling and waste combustion such as incineration of biomass or household waste.
Much of the equipment and infrastructure for EOS will be built in Cyprus, providing local construction and engineering jobs.
Alfa Mediterranean Enterprises Ltd is developing the project on a total area of some 1.8 million sq metres.
Another application of Solastor’s CST technology is a 3 MW facility at Lake Cargellico, also in New South Wales.
Located on the outer limits of the main power grid, the town was susceptible to blackouts and power instability before the solar thermal plant, which consists of eight modules and a steam turbine, started producing electricity in May 2011.
Lloyd Energy Systems won a grant from the Australian government to support construction of the facility but sold its interests in Lake Cargellico in 2011.
The EOS 50 MW CSP project will supply about 5 per cent of Cyprus’s electricity generation, with power on demand, even after sunset.

首批光热发电CSP示范项目有望年底投运并网-香港王建中

甘肃玉门打造“光热小镇”https://www.china5e.com/news/news-1031105-1.html

—国家首批光热发电示范项目有望年底投运并网


2018-06-08  
经济日报 李琛奇 陈发明  


5月下旬的戈壁滩上阳光炽热,位于甘肃玉门市郑家沙窝的5万千瓦光热发电项目建设现场热火朝天。在茫茫戈壁上,工人们正忙着焊接安装各种设备,塔架周边数千根柱子已经安上了光亮的定日镜。
“整个项目共建设15个发电模块,即将完成的是第一个模块。”玉门鑫能光热第一电力有限公司总经理李瑞祥告诉记者,作为国家首批光热发电示范项目之一,郑家沙窝熔盐塔式5万千瓦光热发电项目的建设进度在掌控之中,有望实现年底投运并网目标。
玉门境内太阳能资源非常丰富,是国家一类太阳能资源区,可开发太阳能发电项目面积近3000平方公里,是建设太阳能光伏发电的理想区域,也是甘肃省太阳能总辐射量最高区域之一。
记者了解到,2016年9月份,国家能源局确定了第一批太阳能热发电示范项目共20个、总装机容量134.9万千瓦,其中玉门市共入选示范项目4个、总装机容量25万千瓦。玉门成为此次国家光热项目获批数量最多、装机规模最大、技术路线最全的县市。

                                                 Source: http://www.xinchen-csp.com/about.php?class_id=101


李瑞祥说,郑家沙窝熔盐塔式5万千瓦光热发电项目由上海晶电新能源有限公司和江苏鑫晨光热技术有限公司负责建设,系统转换效率达18.5%,储热时长由6小时优化为12小时。项目建成后,年平均发电量可达2.2亿千瓦时,年可实现销售收入1.43亿元,可节约标煤7.7万吨、减排二氧化碳23万吨,经济效益和节能减排效益非常显著。
随着4个国家首批光热发电示范项目陆续开工建设,玉门市已经开始布局相关产业,打造光热产业小镇。玉门市能源局有关负责人介绍,玉门光热小镇核心区位于玉门市花海镇,规划面积500平方公里。规划形成“一客厅四基地”的主体功能结构:“一客厅”即光热小镇,“四基地”分别为光热发电基地、装备制造基地、技术验证基地和人才培养基地。
项目建成后,玉门光热小镇将把光热发电及装备制造、光热产业研发、检测、人才培养等产业链条完全整合起来,形成强大的产业集聚效应,成为光热技术大规模商业运营的产业高地。
 Source: https://kuaibao.qq.com/s/20180505B15JD200?refer=spider

---------------------------------------------------------------------------

http://www.cspplaza.com/article-10289-1.html



光热特色小镇核心区位于玉门市花海镇,规划面积4011平方公里,计划建设四大专项园区:光热发电产业园区、光热装备制造产业园区、乡村旅游示范区、绿色农产品加工生产园区,以期尽快形成光热产业基地的产业集群效应。

  光热发电产业园区已经获批的国家首批光热示范项目神华国华10万千瓦塔式熔岩光热发电项目已落户基地,浙江中控、浙江盾安、中国联合工程公司、宁波能源等光热发电项目已与玉门市签约,并启动可研编制工作,正在积极准备项目申报工作。

  鲁强介绍,目前国内较为成熟的光热发电类型主要有塔式熔岩发电、线性菲涅尔式发电、槽式导热油发电、蝶式反射发电等四种类型,园区这四种类型的发电技术路线都已占全,也是国内光热发电展示的一个窗口,玉门力争要把小镇建成全国重要的光热发电技术领跑者。

  光热装备制造产业园区则重点发展光热支架、光热板、储热设备、定日镜等光热发电配套装备设备。目前,小镇已与北京首航、江苏联储、杭州帷盛等公司达成了合作协议,届时,将与光热发电园区形成配套完善的装备制造基地,形成辐射新疆、内蒙、青海等全国光热发电主要区域的装备制造基地。

                                              Source: https://kuaibao.qq.com/s/20180505B15JD200?refer=spider